Cadreatech

  • Monday - Friday 8:00am to 5:00pm
  • PIEDMONT PLAZA ANEX, 671 Ngong Road

Setting Out Survey

Setting Out Survey in Kenya | Construction Setting Out | Cadreatech

Engineering Survey Services — Cadreatech

Setting Out Survey Services in Kenya

Precise transfer of approved engineering designs from drawings onto the ground — so your construction team builds exactly to structural intent. Column grids, foundation positions, road alignments, drainage invert levels, and slab reference points.

Total Station

Millimetre-precision layout

RTK GNSS

Coordinate-based positioning

All project types

Buildings, roads, drainage

The service explained

What Is a Setting Out Survey?

Setting out — sometimes called construction layout survey or pegging out — is the process of physically marking the positions, levels, and alignments shown on approved engineering drawings onto the actual ground at a construction site.

It is the critical link between design and construction. The structural engineer's column grid, the architect's building line, the civil engineer's road centreline, and the drainage contractor's pipe invert levels all exist as numbers on a drawing until a setting out survey makes them real and measurable on the ground.

Setting out is carried out using calibrated total stations and RTK GNSS, working from established control points. Physical markers — pegs, steel pins, spray paint, or offset profiles — are placed at key positions to guide the construction team during excavation, formwork, concrete pouring, and structural erection.

What we set out

  • Column grid lines and individual column centre positions
  • Building reference lines and setting-out baselines
  • Foundation excavation limits and formation levels
  • Finished floor levels and slab surface reference points
  • Road centrelines, kerb lines, and carriageway edges
  • Drainage pipe alignments and invert levels
  • Retaining wall and boundary wall alignments
  • Pile positions for piled foundation systems
  • Formwork verticality check and re-setting

When you need a setting out survey

  • Before any excavation begins — to mark foundation positions and depths
  • After bulk excavation — to re-establish column and wall positions in the excavated area
  • Before each concrete pour — to verify formwork positions match design
  • During multi-storey construction — to transfer column positions floor by floor
  • For road and drainage construction — to peg alignments and set pipe levels
  • When contractor peg positions need independent verification before concreting
  • After any redesign or drawing revision affecting structure positions
  • For piled foundations — to mark individual pile positions to design tolerance

Scope of service

What Cadreatech Sets Out

Our setting out service covers the full construction lifecycle — from initial site establishment through structural completion.

📐 Building Column Grid

Establishing the primary column grid from structural drawings using total station traverses from established benchmarks. Individual column positions marked to millimetre tolerance on prepared ground or blinding layer.

⬇️ Foundation Levels

Setting excavation formation levels for pad foundations, strip footings, and raft slabs. Marking offset profiles so levels can be re-established after excavation equipment has disturbed initial pegs.

🏗️ Slab & Floor Levels

Establishing finished floor level (FFL) reference points and screed level controls across slab areas. Checking slab-on-grade or suspended slab soffit levels against structural drawings.

🛣️ Road Centreline

Pegging road centrelines, kerb lines, and carriageway edges from road design alignments. Setting out vertical curves and gradient changes at design chainage intervals.

💧 Drainage Invert Levels

Setting out drainage pipe alignments and marking invert levels at manholes and at regular intervals along drainage runs. Critical for achieving designed pipe gradients and hydraulic performance.

🔩 Pile Positions

Marking individual pile positions from structural drawings for piled foundation systems. Tolerance-controlled positioning with coordinate check report issued after marking.

📏 Verticality Checks

Independent check of formwork verticality and column plumb during structural frame construction. Identifies deviation before concrete is poured when correction is still possible.

🏘️ Multi-Storey Transfer

Transferring column grid lines vertically through a multi-storey structure using optical plumbing or total station. Ensures structural alignment is maintained across all floors.

Why precision matters

The Cost of Getting Setting Out Wrong

Setting out is one of the lowest-cost items in a construction budget — but errors here have among the highest consequences.

❌ When setting out goes wrong

  • Column positioned in wrong place — entire floor slab may need demolition and rebuild
  • Foundation excavated to wrong depth — structural rework and extended programme
  • Drainage pipe set on wrong gradient — sewer backs up, system fails inspection
  • Building line encroaches on boundary — county enforcement and possible demolition
  • Floor level set at wrong elevation — staircase geometry fails, drainage doesn't work
  • Contractor claims against engineer for inadequate setting out information

✅ With Cadreatech setting out

  • All positions transferred directly from approved structural drawings — no estimation
  • Coordinate check report issued confirming each peg position matches design
  • Offset profiles set so pegs can be re-established if disturbed during excavation
  • Independent from the contractor — no conflict of interest on position verification
  • Available for multiple site visits throughout the construction programme
  • Fully documented record of setting out for project file and NCA compliance

Documentation

Setting Out Deliverables

Every setting out engagement is fully documented so the project file records exactly what was marked and when.

01

Setting Out Plan (DWG / PDF)

Drawing showing all pegged positions, offset distances, baseline references, and benchmark locations

02

Coordinate Check Report

Tabular record of designed vs. as-set coordinates for each column position, pile, or reference point

03

Level Record Sheet

Formation levels, finished floor levels, invert levels, and reference benchmarks as set on site

04

Site Photographs

Photographs of each peg or marker with visible reference labels for project records

05

Setting Out Certificate

Signed certificate confirming that positions have been set out in accordance with approved drawings

06

Deviation Report (if applicable)

Report of any discrepancies discovered between as-built positions and design during verification checks

Our process

How We Carry Out Setting Out

1

Drawing Review

We study the approved structural and architectural drawings to extract all coordinates, levels, and grid references needed for setting out

2

Control Establishment

Primary control points and benchmarks established on site using RTK GNSS, tied to project coordinate system

3

Baseline Setting

Main setting out baseline established from two permanent reference points — the backbone for all subsequent measurements

4

Grid & Position Marking

Column grid lines, foundation centres, road centrelines, or drainage alignments marked on the ground using pegs, pins, or profile boards

5

Level Setting

Formation levels, FFL references, and invert levels set using digital level instrument from established benchmarks

6

Documentation Issue

Setting out plan, coordinate check report, level record, and signed certificate issued to contractor and supervising engineer

Frequently asked questions

Setting Out Survey Questions

Who is responsible for setting out on a construction project in Kenya?

In Kenya, setting out is the responsibility of the supervising engineer and contractor working together. The structural engineer defines the positions on drawings; the contractor is responsible for physical setting out on site. However, for accuracy assurance — particularly on formal projects, multi-storey buildings, or infrastructure contracts — an independent engineering surveyor like Cadreatech is engaged to carry out or verify the setting out, separate from the contractor.

How accurate is setting out with a total station?

A well-calibrated total station can achieve positional accuracy of ±2–5mm at typical construction site distances. RTK GNSS achieves ±10–20mm under good satellite conditions. For most building construction in Kenya, total station setting out is the preferred method for precision. We document the accuracy class and instrument calibration status in every setting out report.

Can you verify setting out done by a contractor?

Yes. Independent verification of contractor setting out is a common and valuable service — particularly before major concrete pours where an error cannot be corrected. We can check and formally document whether the contractor's pegged positions match the approved drawings, and issue a report for the supervising engineer's records.

Do I need setting out for a small residential building?

For small residential structures in Kenya, contractors sometimes carry out informal setting out using tapes and profiles. However, even minor positional errors can affect boundary compliance, drainage direction, and structural alignment. For any formal project — particularly those requiring NCA registration or county inspection — documented setting out by a qualified surveyor is recommended and increasingly expected by supervising engineers.

How long does setting out take on a typical building project?

For a standard residential or small commercial building, initial column grid and foundation setting out typically takes half to one full working day on site, plus preparation time reviewing drawings and establishing control. We are available for return visits throughout the construction programme for level transfers, verticality checks, and re-pegging after site disturbance.

Related services

You May Also Need

Request a Setting Out Survey Quote

Share your project type, site location, and the stage of construction you are at. We will confirm availability, provide a quotation, and arrange a drawing review call with your supervising engineer if needed.